Roxby Council
A A A
Email Us
Pump track header w BHP logo

PUMP TRACK UPDATE - September 2019

Thanks to a BHP Community Donation, the design phase of the Roxby Downs Multipurpose Pump Track has now been successfully completed, with all relevant parties having reviewed and approved the final engineering drawings from The Trail Collective.

View key components of the final drawings here:   Roxby Downs Pump Track - Drawings extract Sept 2019(1818 kb)

Ahrens, the official Project and Track Construction Manager, are now busy working on the project construction timeline and scopes of work.  The community will be advised of the expected timeframes once these have been received.

The Municipal Council of Roxby Downs has approved the land use and are actively contributing skilled support for the project.  Council's Sport and Recreation Officer, Group Manager: Essential Services and Assets and Group Manager:  Lifestyle and Sport are all playing key roles in the development of the Pump Track project.

The Sport and Recreation Forum is now seeking local community, business and contractor support for the project.    If you would like to contribute to the successful delivery of the project, the Sport and Recreation Forum would like to hear from you, whether it be a financial contribution, donation of goods or in-kind labour.

Find more information and pledge your support here: https://asf.org.au/projects/roxby-downs-sport-and-recreation-forum/

For further information, please contact Michelle Smith, Sport and Recreation Officer on 0428 723 870 or starclub@jroxbylink.com.au

 

 

PUMP TRACK UPDATE - April 2019

The concept design for Roxby Downs’ multipurpose pump track has been finalised and approved by the Roxby Downs Sport and Recreation Forum.

The pump track now moves to the detailed design phase of technical and civil works specifications and construction methods. This will be completed by The Trail Collective. Once this has been received and approved by the Sport and Recreation Forum, a project control group will commence meeting to organise the construction of the project. The project will also be uploaded onto the Australian Sports Foundation website for local contractors to pledge their support.

What is a concept design?
These drawings represent the vision for the pump track development on a conceptual level. They are a preliminary design which is subject to change, a forecast of the development potential, and a road map to assist in accomplishing the vision from concept to reality.

Below are three images of the concept design for Roxby Downs' multipurpose pump track.

Pump track concept design

Pump track concept design

Pump track concept design

 


 

BACKGROUND

For more information on the background of the multipurpose pump track and past consultations on its design, click here.

 

Contact Council

6 Richardson Place

Roxby Downs SA 5725

Monday to Friday

9.00am - 5.00pm

Closed Public Holidays

PO Box 124

Roxby Downs SA 5725

Phone: (08) 8671 0010

Fax: (08) 8671 0452

Email Us

Roxby Downs South Australia
Top